  1. Q03

    June 2025 · Paper 3

    The whole paper ↗
    June 2025 Paper 3, question 03: VBM’s Operations Director believes that the new factory could be opened in a year. Do you agree? Justify your view by using the data in Appendix C and other inf
  2. Q14

    June 2024 · Paper 1

    The whole paper ↗
    June 2024 Paper 1, question 14: Questions 14 and 15 are based on the network below: Referring to the network above, which one of the following statements is true? [1 mark] A Activity B is not
  3. Q15

    June 2024 · Paper 1

    The whole paper ↗
    June 2024 Paper 1, question 15: Referring to the network shown above: If Activity A is delayed by 3 days, the duration of the critical path will: [1 mark] A not change. B increase by 1 day. C
  4. June 2023 Paper 3, question 06: Many businesses have a strategy of growth. To what extent does the success of a growth strategy for any business depend mainly on its leadership? [24 marks] Bod
  5. Q09

    June 2022 · Paper 1

    The whole paper ↗
    June 2022 Paper 1, question 09: Statement 1: ‘In a network diagram, the path with the lowest total float time is the critical path.’ Statement 2: ‘In a network diagram, at least one activity m
  6. Q16.1

    November 2021 · Paper 1

    The whole paper ↗
    November 2021 Paper 1, question 16.1: State the activities on the critical path. [1 mark] 1 6 Figure 2 shows a network for a project. All timings are shown in days. Figure 2 Network for a project
  7. Q16.2

    November 2021 · Paper 1

    The whole paper ↗
    November 2021 Paper 1, question 16.2: What is the float time, in days, for Activity D? [1 mark] The business has learned that Activity E will now take 7 days to complete. 1 6 Figure 2 shows a networ
  8. Q16.3

    November 2021 · Paper 1

    The whole paper ↗
    November 2021 Paper 1, question 16.3: Given this change, state the activities on the critical path. [1 mark] 1 6 Figure 2 shows a network for a project. All timings are shown in days. Figure 2 Netwo
  9. Q16.4

    November 2021 · Paper 1

    The whole paper ↗
    November 2021 Paper 1, question 16.4: Given this change, what is the duration of this critical path, in days? [1 mark] 1 6 Figure 2 shows a network for a project. All timings are shown in days. Figu
  10. Q04

    November 2021 · Paper 3

    The whole paper ↗
    November 2021 Paper 3, question 04: To what extent is network analysis likely to be useful to AM plc when constructing its new factory? [16 marks] The past Aerial Manufacturing plc (AM plc) manufa
All 10 questions on Managing strategic implementation, as a list
  1. June 2025, Paper 3, Q03 (16 marks): VBM’s Operations Director believes that the new factory could be opened in a year. Do you agree? Justify your view by using the data in Appendix C and other inf
  2. June 2024, Paper 1, Q14 (1 mark): Questions 14 and 15 are based on the network below: Referring to the network above, which one of the following statements is true? [1 mark] A Activity B is not
  3. June 2024, Paper 1, Q15 (1 mark): Referring to the network shown above: If Activity A is delayed by 3 days, the duration of the critical path will: [1 mark] A not change. B increase by 1 day. C
  4. June 2023, Paper 3, Q06 (24 marks): Many businesses have a strategy of growth. To what extent does the success of a growth strategy for any business depend mainly on its leadership? [24 marks] Bod
  5. June 2022, Paper 1, Q09 (1 mark): Statement 1: ‘In a network diagram, the path with the lowest total float time is the critical path.’ Statement 2: ‘In a network diagram, at least one activity m
  6. November 2021, Paper 1, Q16.1 (1 mark): State the activities on the critical path. [1 mark] 1 6 Figure 2 shows a network for a project. All timings are shown in days. Figure 2 Network for a project
  7. November 2021, Paper 1, Q16.2 (1 mark): What is the float time, in days, for Activity D? [1 mark] The business has learned that Activity E will now take 7 days to complete. 1 6 Figure 2 shows a networ
  8. November 2021, Paper 1, Q16.3 (1 mark): Given this change, state the activities on the critical path. [1 mark] 1 6 Figure 2 shows a network for a project. All timings are shown in days. Figure 2 Netwo
  9. November 2021, Paper 1, Q16.4 (1 mark): Given this change, what is the duration of this critical path, in days? [1 mark] 1 6 Figure 2 shows a network for a project. All timings are shown in days. Figu
  10. November 2021, Paper 3, Q04 (16 marks): To what extent is network analysis likely to be useful to AM plc when constructing its new factory? [16 marks] The past Aerial Manufacturing plc (AM plc) manufa

Questions, mark schemes and examiner’s reports are © AQA, from their published past papers. Plumi isn’t affiliated with any exam board. Want whole papers? Full past papers.