Managing strategic implementation: AQA A‑Level Business questions
Every AQA A-Level Business exam question on 3.10.3 Managing strategic implementation, 2020–2025, with its mark scheme and examiner’s report.
Find questions393
Exam
All years
Calculations

![June 2024 Paper 1, question 14: Questions 14 and 15 are based on the network below: Referring to the network above, which one of the following statements is true? [1 mark] A Activity B is not](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/71321-jun24-14-qp.webp)
![June 2024 Paper 1, question 15: Referring to the network shown above: If Activity A is delayed by 3 days, the duration of the critical path will: [1 mark] A not change. B increase by 1 day. C](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/71321-jun24-15-qp.webp)
![June 2023 Paper 3, question 06: Many businesses have a strategy of growth. To what extent does the success of a growth strategy for any business depend mainly on its leadership? [24 marks] Bod](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/71323-jun23-06-qp.webp)

Q16.1
The whole paper ↗![November 2021 Paper 1, question 16.1: State the activities on the critical path. [1 mark] 1 6 Figure 2 shows a network for a project. All timings are shown in days. Figure 2 Network for a project](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/71321-nov21-16-1-qp.webp)
Q16.2
The whole paper ↗![November 2021 Paper 1, question 16.2: What is the float time, in days, for Activity D? [1 mark] The business has learned that Activity E will now take 7 days to complete. 1 6 Figure 2 shows a networ](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/71321-nov21-16-2-qp.webp)
Q16.3
The whole paper ↗![November 2021 Paper 1, question 16.3: Given this change, state the activities on the critical path. [1 mark] 1 6 Figure 2 shows a network for a project. All timings are shown in days. Figure 2 Netwo](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/71321-nov21-16-3-qp.webp)
Q16.4
The whole paper ↗![November 2021 Paper 1, question 16.4: Given this change, what is the duration of this critical path, in days? [1 mark] 1 6 Figure 2 shows a network for a project. All timings are shown in days. Figu](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/71321-nov21-16-4-qp.webp)
![November 2021 Paper 3, question 04: To what extent is network analysis likely to be useful to AM plc when constructing its new factory? [16 marks] The past Aerial Manufacturing plc (AM plc) manufa](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/71323-nov21-04-qp.webp)
All 10 questions on Managing strategic implementation, as a list
- June 2025, Paper 3, Q03 (16 marks): VBM’s Operations Director believes that the new factory could be opened in a year. Do you agree? Justify your view by using the data in Appendix C and other inf
- June 2024, Paper 1, Q14 (1 mark): Questions 14 and 15 are based on the network below: Referring to the network above, which one of the following statements is true? [1 mark] A Activity B is not
- June 2024, Paper 1, Q15 (1 mark): Referring to the network shown above: If Activity A is delayed by 3 days, the duration of the critical path will: [1 mark] A not change. B increase by 1 day. C
- June 2023, Paper 3, Q06 (24 marks): Many businesses have a strategy of growth. To what extent does the success of a growth strategy for any business depend mainly on its leadership? [24 marks] Bod
- June 2022, Paper 1, Q09 (1 mark): Statement 1: ‘In a network diagram, the path with the lowest total float time is the critical path.’ Statement 2: ‘In a network diagram, at least one activity m
- November 2021, Paper 1, Q16.1 (1 mark): State the activities on the critical path. [1 mark] 1 6 Figure 2 shows a network for a project. All timings are shown in days. Figure 2 Network for a project
- November 2021, Paper 1, Q16.2 (1 mark): What is the float time, in days, for Activity D? [1 mark] The business has learned that Activity E will now take 7 days to complete. 1 6 Figure 2 shows a networ
- November 2021, Paper 1, Q16.3 (1 mark): Given this change, state the activities on the critical path. [1 mark] 1 6 Figure 2 shows a network for a project. All timings are shown in days. Figure 2 Netwo
- November 2021, Paper 1, Q16.4 (1 mark): Given this change, what is the duration of this critical path, in days? [1 mark] 1 6 Figure 2 shows a network for a project. All timings are shown in days. Figu
- November 2021, Paper 3, Q04 (16 marks): To what extent is network analysis likely to be useful to AM plc when constructing its new factory? [16 marks] The past Aerial Manufacturing plc (AM plc) manufa
Questions, mark schemes and examiner’s reports are © AQA, from their published past papers. Plumi isn’t affiliated with any exam board. Want whole papers? Full past papers.
Rather write your answers by hand on iPad? Plumi marks them against the same mark schemes.