Critical path analysis: OCR A‑Level Further Maths questions

Every OCR A-Level Further Maths exam question on D.3 Critical path analysis, 2018–2025, with its mark scheme and examiner’s report.

Find questions648

648 questions

  1. Q4

    June 2025 · Discrete Mathematics

    The whole paper ↗
    June 2025 Discrete Mathematics, question 4: The table shows the activities involved in a project, together with the immediate predecessors and the duration of each activity in hours. Immediate Duration Ac
  2. Q6

    June 2025 · AS Discrete Mathematics

    The whole paper ↗
    June 2025 AS Discrete Mathematics, question 6: The table shows the activities involved in a project, together with their immediate predecessors and the duration of each activity in hours. Activity Duration I
  3. Q4

    June 2024 · Discrete Mathematics

    The whole paper ↗
    June 2024 Discrete Mathematics, question 4: A project is represented by the activity network below. The activity durations are given in hours. C(5) A(2) F(2) D(3) G(1) B(4) E(1) (a) By carrying out a forw
  4. Q4

    June 2024 · AS Discrete Mathematics

    The whole paper ↗
    June 2024 AS Discrete Mathematics, question 4: A project is represented by the activity network below. The activity durations are given in minutes. C(3) 3 2 E(2) A(2) 0 D(2) 5 B(4) F(1) 1 4 (a) Give the reas
  5. Q1

    June 2023 · Discrete Mathematics

    The whole paper ↗
    June 2023 Discrete Mathematics, question 1: The table below shows the activities involved in a project together with the immediate predecessors and the duration of each activity. Activity Immediate predec
  6. Q5

    June 2023 · AS Discrete Mathematics

    The whole paper ↗
    June 2023 AS Discrete Mathematics, question 5: Hiro has been asked to organise a quiz. The table below shows the activities involved, together with the immediate predecessors and the duration of each activit
  7. Q2

    June 2022 · Discrete Mathematics

    The whole paper ↗
    June 2022 Discrete Mathematics, question 2: The table below shows the activities involved in a project together with the immediate predecessors and the duration of each activity. Activity Immediate predec
  8. Q2

    June 2022 · AS Discrete Mathematics

    The whole paper ↗
    June 2022 AS Discrete Mathematics, question 2: The activities involved in a project and their durations, in hours, are represented in the activity network below. A(5) C(6) F(3) D(4) B(3) G(4) E(2) (a) Carry
  9. Q6

    November 2021 · AS Discrete Mathematics

    The whole paper ↗
    November 2021 AS Discrete Mathematics, question 6: Sarah is having some work done on her garden. The table below shows the activities involved, their durations and their immediate predecessors. These durations a
  10. Q6

    November 2020 · Discrete Mathematics

    The whole paper ↗
    November 2020 Discrete Mathematics, question 6: A project is represented by the activity on arc network below. 3 7 D(4) J(2) A(4) E(2) 1 5 8 I(x) H(3) F(3) B(2) K(5) 2 C(1) 4 G(5) 6 The duration of each activ
  11. Q4

    November 2020 · AS Discrete Mathematics

    The whole paper ↗
    November 2020 AS Discrete Mathematics, question 4: Bob is extending his attic with the help of some friends, including his architect friend Archie. The activities involved, their durations (in days) and Bob’s no
  12. Q2

    June 2019 · Discrete Mathematics

    The whole paper ↗
    June 2019 Discrete Mathematics, question 2: A project is represented by the activity network and cascade chart below. The table showing the number of workers needed for each activity is incomplete. Each a
  13. Q4

    June 2019 · AS Discrete Mathematics

    The whole paper ↗
    June 2019 AS Discrete Mathematics, question 4: The table shows the activities involved in a project, their durations in hours and their immediate predecessors. The activities can be represented as an activit
  14. Q6

    June 2018 · AS Discrete Mathematics

    The whole paper ↗
    June 2018 AS Discrete Mathematics, question 6: Sheona and Tim are making a short film. The activities involved, their durations and immediate predecessors are given in the table below. Activity Duration (day
All 14 questions on Critical path analysis, as a list
  1. June 2025, Discrete Mathematics, Q4 (14 marks): The table shows the activities involved in a project, together with the immediate predecessors and the duration of each activity in hours. Immediate Duration Ac
  2. June 2025, AS Discrete Mathematics, Q6 (9 marks): The table shows the activities involved in a project, together with their immediate predecessors and the duration of each activity in hours. Activity Duration I
  3. June 2024, Discrete Mathematics, Q4 (16 marks): A project is represented by the activity network below. The activity durations are given in hours. C(5) A(2) F(2) D(3) G(1) B(4) E(1) (a) By carrying out a forw
  4. June 2024, AS Discrete Mathematics, Q4 (9 marks): A project is represented by the activity network below. The activity durations are given in minutes. C(3) 3 2 E(2) A(2) 0 D(2) 5 B(4) F(1) 1 4 (a) Give the reas
  5. June 2023, Discrete Mathematics, Q1 (7 marks): The table below shows the activities involved in a project together with the immediate predecessors and the duration of each activity. Activity Immediate predec
  6. June 2023, AS Discrete Mathematics, Q5 (11 marks): Hiro has been asked to organise a quiz. The table below shows the activities involved, together with the immediate predecessors and the duration of each activit
  7. June 2022, Discrete Mathematics, Q2 (9 marks): The table below shows the activities involved in a project together with the immediate predecessors and the duration of each activity. Activity Immediate predec
  8. June 2022, AS Discrete Mathematics, Q2 (7 marks): The activities involved in a project and their durations, in hours, are represented in the activity network below. A(5) C(6) F(3) D(4) B(3) G(4) E(2) (a) Carry
  9. November 2021, AS Discrete Mathematics, Q6 (11 marks): Sarah is having some work done on her garden. The table below shows the activities involved, their durations and their immediate predecessors. These durations a
  10. November 2020, Discrete Mathematics, Q6 (13 marks): A project is represented by the activity on arc network below. 3 7 D(4) J(2) A(4) E(2) 1 5 8 I(x) H(3) F(3) B(2) K(5) 2 C(1) 4 G(5) 6 The duration of each activ
  11. November 2020, AS Discrete Mathematics, Q4 (10 marks): Bob is extending his attic with the help of some friends, including his architect friend Archie. The activities involved, their durations (in days) and Bob’s no
  12. June 2019, Discrete Mathematics, Q2 (7 marks): A project is represented by the activity network and cascade chart below. The table showing the number of workers needed for each activity is incomplete. Each a
  13. June 2019, AS Discrete Mathematics, Q4 (10 marks): The table shows the activities involved in a project, their durations in hours and their immediate predecessors. The activities can be represented as an activit
  14. June 2018, AS Discrete Mathematics, Q6 (17 marks): Sheona and Tim are making a short film. The activities involved, their durations and immediate predecessors are given in the table below. Activity Duration (day

Questions, mark schemes and examiner’s reports are © OCR, from their published past papers. Plumi isn’t affiliated with any exam board. Want whole papers? Every OCR A-Level Further Maths paper.

Rather write your answers by hand on iPad? Plumi marks them against the same mark schemes.