Project management: OCR A‑Level Business questions
Every OCR A-Level Business exam question on Project management, 2021–2025, with its mark scheme and examiner’s report.
Paper
All papers
Exam
All years
Calculations
- Your answer
- 0 words
- 0 words
- 0 words
- 0 words
- 0 words
- 0 words
- Your answer
All 8 questions on Project management, as a list
- June 2025, Paper 1, Q5 (1 mark): The schedule for a project is shown in the network diagram. All timings are in weeks. 13 3 13 B D 4 30 A F 0 9 43 84 1 2 5 6 0 9 43 84 9 41 C E 5 15 14 2 28 Ass
- June 2024, Paper 1, Q17 (6 marks): ‘…projects have always been managed to a high standard, but they are becoming ever more complex.’ (lines 43–44) Analyse one advantage to Dev of using Gantt char
- June 2023, Paper 3, Q8(b)(i) (1 mark): Identify the latest finish time for this activity. [1]
- June 2023, Paper 3, Q8(b)(ii) (1 mark): Calculate the total float for this activity. [1]
- June 2023, Paper 3, Q9 (2 marks): Explain one qualitative factor which might affect project management in a business. [2]
- June 2022, Paper 3, Q6(b)(i) (1 mark): Identify the earliest start time for this activity. [1]
- June 2022, Paper 3, Q6(b)(ii) (2 marks): Calculate the free float for this activity. [2]
- November 2021, Paper 1, Q13 (1 mark): A supermarket chain has decided to upgrade the technology used in its distribution warehouse. The warehouse will need to be closed while the electrical work and