Decision-making models: WJEC A‑Level Business questions
Every WJEC A-Level Business exam question on 3.8 Decision-making models, 2016–2025, with its mark scheme and examiner’s report.
Find questions410
Exam
All years
Calculations
Q4(a)(i)
The whole paper ↗![Summer 2025 Unit 3, question 4(a)(i): Private cost. [2]](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u30-jun25-04-ai-qp.webp)
Q4(a)(ii)
The whole paper ↗![Summer 2025 Unit 3, question 4(a)(ii): External benefit. [2]](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u30-jun25-04-aii-qp.webp)
Q4(b)
The whole paper ↗![Summer 2025 Unit 3, question 4(b): Assess the advantages and disadvantages of using cost benefit analysis for business decision-making. [8] Additional space for Question 4(b) only.](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u30-jun25-04-b-qp.webp)
Q6(a)(i)
The whole paper ↗![Summer 2024 Unit 3, question 6(a)(i): Complete the network diagram below, including the time required for each task, the earliest start times and the latest finishing times. [5]](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u30-jun24-06-ai-qp.webp)
Q6(a)(ii)
The whole paper ↗![Summer 2024 Unit 3, question 6(a)(ii): Mark on the diagram the critical path. [1] C D K B M A N E L F G H J](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u30-jun24-06-aii-qp.webp)
Q6(b)
The whole paper ↗![Summer 2024 Unit 3, question 6(b): With reference to your completed critical path analysis diagram, evaluate its usefulness to Lewis Construction Ltd. [9] Additional page, if required. Question n](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u30-jun24-06-b-qp.webp)
Q4(a)
The whole paper ↗
Q4(b)
The whole paper ↗
Q4(c)
The whole paper ↗
![Summer 2023 Unit 4, question 2.1: Decision-making 2 1 Describe the difference between strategic decisions and operational decisions made by a national retail business. [10]](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u40-jun23-02-a-qp.webp)
![Summer 2023 Unit 4, question 2.2: Decision-making 2 2 Evaluate the view that using quantitative decision-making models will guarantee the success of a business. [20]](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u40-jun23-02-b-qp.webp)

Q3(a)(i)
The whole paper ↗![Summer 2018 Unit 3, question 3(a)(i): With the use of table 1, fully complete the decision tree diagram including the expected values of A, B and C. [6]](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u30-jun18-03-ai-qp.webp)
Q3(a)(ii)
The whole paper ↗![Summer 2018 Unit 3, question 3(a)(ii): Calculate the profitability of each of the three options. [2]](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u30-jun18-03-aii-qp.webp)
Q3(b)
The whole paper ↗![Summer 2018 Unit 3, question 3(b): Evaluate the usefulness of decision tree analysis to Fast Snacks PLC. [8]](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u30-jun18-03-b-qp.webp)
Q3(a)
The whole paper ↗![Summer 2018 Unit 4, question 3(a): Describe the likely public costs and benefits of building a new motorway to connect North Wales to South Wales. [10]](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u40-jun18-03-a-qp.webp)
Q3(b)
The whole paper ↗![Summer 2018 Unit 4, question 3(b): ‘Public costs and benefits will always be less valued by businesses than private costs and benefits.’ Discuss. [20]](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u40-jun18-03-b-qp.webp)
Q4(a)
The whole paper ↗
Q4(b)
The whole paper ↗![Summer 2017 Unit 3, question 4(b): Mark the critical path on the diagram. [1]](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u30-jun17-04-b-qp.webp)
Q4(c)
The whole paper ↗![Summer 2017 Unit 3, question 4(c): Discuss the usefulness of critical path analysis to businesses such as Mine-All-Mine. [8]](https://pub-e8a9dbab8e2a4d089f52b2a45e0d0b50.r2.dev/bank/1510u30-jun17-04-c-qp.webp)
All 20 questions on Decision-making models, as a list
- Summer 2025, Unit 3, Q4(a)(i) (2 marks): Private cost. [2]
- Summer 2025, Unit 3, Q4(a)(ii) (2 marks): External benefit. [2]
- Summer 2025, Unit 3, Q4(b) (8 marks): Assess the advantages and disadvantages of using cost benefit analysis for business decision-making. [8] Additional space for Question 4(b) only.
- Summer 2024, Unit 3, Q6(a)(i) (5 marks): Complete the network diagram below, including the time required for each task, the earliest start times and the latest finishing times. [5]
- Summer 2024, Unit 3, Q6(a)(ii) (1 mark): Mark on the diagram the critical path. [1] C D K B M A N E L F G H J
- Summer 2024, Unit 3, Q6(b) (9 marks): With reference to your completed critical path analysis diagram, evaluate its usefulness to Lewis Construction Ltd. [9] Additional page, if required. Question n
- Summer 2023, Unit 3, Q4(a) (4 marks): GFK Windows Ltd is a business that produces, sells and installs double glazing windows, doors and conservatories. The business was established in 1990, it is ow
- Summer 2023, Unit 3, Q4(b) (7 marks): GFK Windows Ltd is a business that produces, sells and installs double glazing windows, doors and conservatories. The business was established in 1990, it is ow
- Summer 2023, Unit 3, Q4(c) (6 marks): GFK Windows Ltd is a business that produces, sells and installs double glazing windows, doors and conservatories. The business was established in 1990, it is ow
- Summer 2023, Unit 4, Q2.1 (10 marks): Decision-making 2 1 Describe the difference between strategic decisions and operational decisions made by a national retail business. [10]
- Summer 2023, Unit 4, Q2.2 (20 marks): Decision-making 2 2 Evaluate the view that using quantitative decision-making models will guarantee the success of a business. [20]
- Summer 2019, Unit 3, Q5 (10 marks): HS2 cost and benefit debate not over The government insists the £56 billion proposal for the HS2 high-speed rail link between London and Birmingham, and eventua
- Summer 2018, Unit 3, Q3(a)(i) (6 marks): With the use of table 1, fully complete the decision tree diagram including the expected values of A, B and C. [6]
- Summer 2018, Unit 3, Q3(a)(ii) (2 marks): Calculate the profitability of each of the three options. [2]
- Summer 2018, Unit 3, Q3(b) (8 marks): Evaluate the usefulness of decision tree analysis to Fast Snacks PLC. [8]
- Summer 2018, Unit 4, Q3(a) (10 marks): Describe the likely public costs and benefits of building a new motorway to connect North Wales to South Wales. [10]
- Summer 2018, Unit 4, Q3(b) (20 marks): ‘Public costs and benefits will always be less valued by businesses than private costs and benefits.’ Discuss. [20]
- Summer 2017, Unit 3, Q4(a) (4 marks): Using the data in Table 1, complete the network diagram below, including: labelling the activities the time required for each task calculate the earliest start
- Summer 2017, Unit 3, Q4(b) (1 mark): Mark the critical path on the diagram. [1]
- Summer 2017, Unit 3, Q4(c) (8 marks): Discuss the usefulness of critical path analysis to businesses such as Mine-All-Mine. [8]
Questions, mark schemes and examiner’s reports are © WJEC CBAC Ltd, from their published past papers. Plumi isn’t affiliated with any exam board. Want whole papers? Full past papers.