Critical path analysis: Edexcel International A Level Maths questions
Every Edexcel International A Level Maths exam question on D1.4 Critical path analysis, 2019–2025, with its mark scheme and examiner’s report.
Paper
All papers
Exam
All years
All 24 questions on Critical path analysis, as a list
- June 2025, AS Decision 1 (D1), Q7 (16 marks): A C B D I E F G H L K J M N Figure 3 A project is modelled by the activity network shown in Figure 3. The activities are represented by the arcs. The number in
- January 2025, AS Decision 1 (D1), Q4 (6 marks): Activity Immediately preceding activities A ‑ B ‑ C ‑ D A E A, B, C F A, B, C G C H D, E, F I F J F, G K F, G (a) Draw the activity network described in the pre
- January 2025, AS Decision 1 (D1), Q7 (14 marks): 1 3 5 8 11 10 9 6 4 2 7 A C B F G H K J I E D L P M R Q N Figure 3 A project is modelled by the activity network shown in Figure 3. The activities are represent
- June 2024, AS Decision 1 (D1), Q2 (10 marks): A B C D E F G H I J K L M N Figure 1 [The sum of the durations of all the activities is 59 days.] The network in Figure 1 shows the activities that need to be u
- June 2024, AS Decision 1 (D1), Q6 (10 marks): Activity Immediately preceding activities A ‑ B ‑ C A D ‑ E A, B, D F D G A, B, D H F, G I A J F, G K C, E, H, I L I M C, E, H, I (a) Draw the activity network
- January 2024, AS Decision 1 (D1), Q1 (13 marks): A B C D E F G H J I K L Figure 1 A project is modelled by the activity network shown in Figure 1. The activities are represented by the arcs. The number in brac
- January 2024, AS Decision 1 (D1), Q4 (7 marks): Activity Immediately preceding activities A – B – C A, B D A, B E B F C, D, E G F H B I F J F K G L G, H, I, J M G, I (a) Draw the activity network described in
- June 2023, AS Decision 1 (D1), Q1 (10 marks): A B C D E F G H I J K L M N P Q Figure 1 A project is modelled by the activity network shown in Figure 1. The activities are represented by the arcs. The number
- June 2023, AS Decision 1 (D1), Q5 (7 marks): Activity Immediately preceding activities A - B - C - D A E A F B, C, E G B, C, E H C I C J D, F, G, H, I K D, F, G, H, I L I (a) Draw the activity network desc
- January 2023, AS Decision 1 (D1), Q4 (13 marks): Activity Immediately preceded by Activity Immediately preceded by Activity Immediately preceded by A – G M D, G B – H N C – I P D A J Q E C K D, G R F C L D, G
- June 2022, AS Decision 1 (D1), Q2 (11 marks): 13 22 26 9 0 0 A B C D E F G H I( y) J K L M N(x) 26 Figure 1 The network in Figure 1 shows the activities that need to be undertaken to complete a project. Eac
- June 2022, AS Decision 1 (D1), Q5 (9 marks): The precedence table shows the eleven activities required to complete a project. Activity Immediately preceding activities A – B – C – D A, B E A, B F B, C G B,
- January 2022, AS Decision 1 (D1), Q3 (5 marks): Activity Immediately preceding activities A – B – C – D A, B, C E A, B, C F C G F H D I D, E, G J D, E
- January 2022, AS Decision 1 (D1), Q4 (10 marks):
- October 2021, AS Decision 1 (D1), Q4 (11 marks): 12 13 5 x 0 0 13 13 20 20 y z 25 25 6 6 20 21 F(w) C(v) A B J E D H K L G I M Figure 2 The network in Figure 2 shows the activities that need to be carried out
- June 2021, AS Decision 1 (D1), Q2 (10 marks): D G A F N P K H M C E J I B L Q Figure 1 A project is modelled by the activity network shown in Figure 1. The activities are represented by the arcs. The number
- June 2021, AS Decision 1 (D1), Q6 (9 marks): Activity Immediately preceding activities A – B – C – D A E A F A, B, C G C H G I D, E, F, H J I K I L I M L (a) Draw the activity network for the project descr
- January 2021, AS Decision 1 (D1), Q6 (13 marks): Activity Duration (days) Immediately preceding activities A 4 – B 7 – C 6 – D 10 A E 5 A F 7 C G 6 B, C, E H 6 B, C, E I 7 B, C, E J 9 D, H K 8 B, C, E L 4 F, G
- October 2020, AS Decision 1 (D1), Q4 (7 marks): (a) Draw the activity network described by the precedence table below, using activity on arc. Use dummies only where necessary. Activity Immediately preceding a
- October 2020, AS Decision 1 (D1), Q5 (12 marks): A D J M C B E H F G I K P L N Figure 1 A project is modelled by the activity network shown in Figure 1. The activities are represented by the arcs. The number i
- January 2020, AS Decision 1 (D1), Q3 (9 marks): 24 24 4 10 7 y 0 0 7 7 z 17 17 17 33 33 28 33 H M L K J D(x) E F G C B A I Figure 2 The network in Figure 2 shows the activities that need to be undertaken by a
- January 2020, AS Decision 1 (D1), Q5 (7 marks): Activity Immediately preceding activities A – B – C – D A E C F A, B, C G A, B, C H D, F, G I A, B, C J D, F, G K H L D, E, F, G, I (a) Draw the activity networ
- June 2019, AS Decision 1 (D1), Q4 (12 marks): D J E B A I H G C F 1 2 3 4 K 6 7 5 L N 9 8 M Figure 3 A project is modelled by the activity network shown in Figure 3. The activities are represented by the ar
- June 2019, AS Decision 1 (D1), Q6 (8 marks): Activity Immediately preceding activities A – B – C – D – E A F A, B, C G C H C I D, H J E K E L F, G, I M G, I (a) Draw the activity network described in the p
Questions, mark schemes and examiner’s reports are © Pearson Edexcel, from their published past papers. Plumi isn’t affiliated with any exam board. Want whole papers? Every Edexcel International A Level Maths paper.
Rather write your answers by hand on iPad? Plumi marks them against the same mark schemes.