Scheduling and resource levelling: OCR MEI A‑Level Further Maths questions

OCR MEI A-Level Further Maths past-paper questions on 3.2 Scheduling and resource levelling, 2018–2025, with mark schemes and examiner’s reports where available. Add MadAsMaths questions to your practice, or browse them separately by topic and difficulty.

Questions from
Paper
All papers
Exam
All years

841 questions

  1. Q3

    June 2025 · Modelling with Algorithms

    The whole paper ↗

    Loading the question…

    Open the full PDF
  2. Q5

    June 2024 · Modelling with Algorithms

    The whole paper ↗

    Loading the question…

    Open the full PDF
  3. Q3

    June 2024 · AS Modelling with Algorithms

    The whole paper ↗

    Loading the question…

    Open the full PDF
  4. Q4

    June 2023 · AS Modelling with Algorithms

    The whole paper ↗

    Loading the question…

    Open the full PDF
  5. Q3

    June 2022 · Modelling with Algorithms

    The whole paper ↗

    Loading the question…

    Open the full PDF
  6. Q4

    June 2022 · AS Modelling with Algorithms

    The whole paper ↗

    Loading the question…

    Open the full PDF
  7. Q2

    June 2019 · Modelling with Algorithms

    The whole paper ↗

    Loading the question…

    Open the full PDF
All 7 questions on Scheduling and resource levelling, as a list
  1. June 2025, Modelling with Algorithms, Q3 (12 marks): The table lists the duration (in hours) and immediate predecessors for each activity in a project. Duration Immediate Activity (hours) predecessors A 3 – B 5 A
  2. June 2024, Modelling with Algorithms, Q5 (11 marks): The table in Fig. 5.1 lists the immediate predecessors for each of the eleven activities in a project. Fig. 5.1 Activity Immediate predecessors A - B - C - D A
  3. June 2024, AS Modelling with Algorithms, Q3 (10 marks): The diagram shows an activity network for a project. The number in brackets show the duration of these activities in hours. F(7) A (4) G(4) J (4) D (2) B(3) K(3
  4. June 2023, AS Modelling with Algorithms, Q4 (12 marks): Fig. 4.1 shows an activity network for a project. The arc weights show activity durations in days. Fig. 4.1 D(8) E(4) I(6) A(4) K(8) B(7) F(7) J(11) G(3) C(5) L
  5. June 2022, Modelling with Algorithms, Q3 (6 marks): Activity Independent Float A 0 5 12 7 14 D B 7 C 0 J A I D 0 14 14 B E 0 0 0 20 20 G F 2 E G 2 H K C H 0 F 10 10 17 17 I 0 J 1 K 0 Fig. 3.1 Fig. 3.2 Fig. 3.1 sh
  6. June 2022, AS Modelling with Algorithms, Q4 (13 marks): Fig. 4.1 shows an activity network for a project. The arc weights show activity duration in hours. J(y) D(2) K(7) A(5) E(4) B(x) I(2) F(8) C(3) L(5) G(1) H(7) F
  7. June 2019, Modelling with Algorithms, Q2 (13 marks): The table in Fig. 2.1 lists the duration (in minutes) and immediate predecessors for each activity in a project. Activity Duration Immediate (minutes) predecess