Scheduling and resource levelling: Edexcel A‑Level Further Maths questions

Edexcel A-Level Further Maths past-paper questions on 3.2 Scheduling and resource levelling, 2018–2025, with mark schemes and examiner’s reports where available. Add MadAsMaths questions to your practice, or browse them separately by topic and difficulty.

Questions from
Paper
All papers
Exam
All years

789 questions

  1. Loading the question…

    Open the full PDF
  2. Loading the question…

    Open the full PDF
  3. Loading the question…

    Open the full PDF
  4. Loading the question…

    Open the full PDF
  5. Loading the question…

    Open the full PDF
  6. Loading the question…

    Open the full PDF
  7. Loading the question…

    Open the full PDF
  8. Loading the question…

    Open the full PDF
  9. Q2

    November 2020 · AS Decision 1

    The whole paper ↗

    Loading the question…

    Open the full PDF
All 9 questions on Scheduling and resource levelling, as a list
  1. June 2025, Decision 1, Q6 (13 marks): A(2) D(7) H(6) J(2) M(7) L(10) I(10) K(6) F(5) E(4) G(5) B(4) C(3) Figure 3 A project is modelled by the activity network shown in Figure 3. The activities are
  2. June 2024, Decision 1, Q6 (11 marks): The precedence table below shows the 12 activities required to complete a project. Activity Immediately preceding activities A – B – C – D A E A, B, C F A, B, C
  3. June 2023, Decision 1, Q2 (7 marks): A(3) D(7) G(4) B(5) E(1) H(1) C(4) F(2) Figure 3 The network in Figure 3 shows the activities that need to be undertaken to complete a project. Each activity is
  4. June 2023, Decision 1, Q6 (9 marks): The precedence table below shows the twelve activities required to complete a project. Activity Immediately preceding activities A – B – C – D A E A, B F D, E G
  5. June 2023, AS Decision 1, Q2 (10 marks): A(6) B(10) C(7) D(7) E(8) F(11) G(5) H(9) I(2) J(6) K(9) L(5) 1 3 7 4 6 8 2 5 Figure 1 A project is modelled by the activity network shown in Figure 1. The acti
  6. June 2022, Decision 1, Q5 (14 marks): 4 D(x) A(4) C(7) E(4) G(3) H(5) J(7) K(6) B(5) 14 22 11 0 7 16 F(x) Figure 2 The network in Figure 2 shows the activities that need to be completed for a projec
  7. November 2021, Decision 1, Q2 (9 marks): D(2) B(6) C(10) A(4) E(4) F(5) G(6) H(7) I(2) K(6) L(7) M(5) J(7) Figure 2 A project is modelled by the activity network shown in Figure 2. The activities are r
  8. November 2020, Decision 1, Q2 (15 marks): A(6) B(7) C(5) G(4) H(3) D(4) E(5) I(4) F(3) K(5) L(6) J(6) Figure 1 The network in Figure 1 shows the activities that need to be undertaken to complete a proje
  9. November 2020, AS Decision 1, Q2 (14 marks): D(6) E(8) F(5) G(3) H(7) A(5) B(3) C(4) I(8) J(9) K(6) Figure 1 A project is modelled by the activity network shown in Figure 1. The activities are represented