Critical activities and critical paths: AQA Level 3 Core Maths questions
AQA Level 3 Core Maths past-paper questions on R2 Critical activities and critical paths, 2016–2025, with mark schemes and examiner’s reports where available.
Paper
All papers
Exam
All years
Loading the full question list…
All 13 questions on Critical activities and critical paths, as a list
- June 2025, Paper 2B, Q3 (9 marks): Desalination is the process of removing salt from sea water. A company is hired to build a desalination plant. The table lists the activities which need to be c
- June 2024, Paper 2B, Q5 (12 marks): Pavlova is a dessert made with meringue, fruit and cream. Meringue is made with a baked mixture of egg whites and sugar. The table lists the activities needed t
- June 2023, Paper 2B, Q3 (9 marks): Daisy’s house is being renovated. The table lists the activities needed for the renovation. Task Activity Immediate predecessor(s) Duration (days) A House prepa
- June 2023, Paper 2B, Q5 (6 marks): Noah is a wedding organiser. A wedding he is organising is made up of ten activities. He has started to draw this activity network. Durations are shown in weeks
- June 2022, Paper 2B, Q5 (14 marks): An office is being redecorated. The project manager started to draw an activity network for the project. The unfinished network is on the opposite page. 5 (a) C
- November 2021, Paper 2B, Q4 (15 marks): A company is planning to redesign its website to include some new features. The company will carry out research on how customers navigate the current website. T
- June 2019, Paper 2B, Q4 (14 marks): A toy company has a contract to supply a new kind of toy for a supermarket. The toy company will design and make the toys. The packaging will be made by another
- June 2018, Paper 2B, Q5 (14 marks): Sandy is a builder. She is planning to renovate a conservatory for a customer. Some of the activities required for the project are listed below. A Discuss plans
- June 2017, Paper 2B, Q3 (13 marks): A project manager is overseeing a software development project. The table below lists the activities needed for this project, together with the duration of each
- June 2016, Paper 2B, Q3 (5 marks): After a passenger plane lands at an airport there is a limited amount of time to get the plane ready for its next flight. The table shows the activities after a
- June 2016, Paper 2B, Q7 (14 marks): Dan and his friends are planning a one-day music festival. They have divided the work into a number of activities. The table below shows l the activities l the
- Specimen, Paper 2B, Q4 (8 marks): Monty’s garden is overgrown and needs to be completely redesigned. He has divided the work involved into a number of tasks. The table below shows • the minimum
- Specimen, Paper 2B, Q6 (11 marks): A quiz book is to be written. The work involved has been divided into a number of activities, as shown in the table below. The minimum duration needed to comple