Critical path analysis: AQA A‑Level Further Maths questions
Every AQA A-Level Further Maths exam question on DE Critical path analysis, 2019–2025, with its mark scheme and examiner’s report.
Paper
All papers
Exam
All years
All 14 questions on Critical path analysis, as a list
- June 2025, Paper 3 Discrete, Q5 (6 marks): A project is being planned by Lepton Electricity Installations. The project is broken down into 10 separate activities A, B, …, J and the activity network for t
- June 2025, AS Paper 2 Discrete, Q5 (5 marks): A project consists of 10 activities A, B, C, D, E, F, G, H, I and J The activity network for the project along with the duration, in days, of each activity is s
- June 2024, Paper 3 Discrete, Q10 (7 marks): A project is undertaken by Higton Engineering Ltd. The project is broken down into 11 separate activities A, B, ..., K Figure 3 below shows a completed activity
- June 2024, AS Paper 2 Discrete, Q9 (6 marks): Robert, a project manager, and his team of builders are working on a small building project. Robert has divided the project into ten activities labelled A, B, C
- June 2023, Paper 3 Discrete, Q7 (8 marks): Nova Merit Construction are planning a building project. The planning involves producing an activity network for the project, which is shown in Figure 1 below.
- June 2023, AS Paper 2 Discrete, Q4 (7 marks): A community project consists of 10 activities A, B, . . . , J, as shown in the activity network below. C 8 D 4 E 8 Latest finish time Duration Earliest start ti
- June 2022, Paper 3 Discrete, Q3 (1 mark): A company undertakes a project which consists of 12 activities, A, B, C, …, L Each activity requires one worker. The resource histogram below shows the duration
- June 2022, Paper 3 Discrete, Q6 (6 marks): Bill Durrh Ltd undertake a construction project. The activity network for the project is shown below. The duration of each activity is given in weeks. C 0 5 F 5
- June 2022, AS Paper 2 Discrete, Q3 (4 marks): A project consists of 11 activities A, B, …, K A completed activity network for the project is shown in the diagram below. A 0 7 B 0 6 C 0 5 H 2 I 3 J 5 18 12 1
- November 2021, Paper 3 Discrete, Q1 (1 mark): Which of the following statements about critical path analysis is always true? Tick (3) one box. [1 mark] All activity networks have exactly one critical path.
- November 2021, AS Paper 2 Discrete, Q1 (2 marks): (a) A project consists of three activities A, B and C An activity network for the project is shown in the diagram below. A 0 5 y B 0 7 z C x 8 15 Duration Lates
- November 2020, AS Paper 2 Discrete, Q5 (6 marks): A restoration project is divided into a number of activities. The duration and predecessor(s) of each activity are shown in the table below. Activity Immediate
- June 2019, Paper 3 Discrete, Q8 (10 marks): A motor racing team is undertaking a project to build next season’s racing car. The project is broken down into 12 separate activities A, B, ..., L, as shown in
- June 2019, AS Paper 2 Discrete, Q2 (1 mark): Part of an activity network is shown in the diagram below. ABC is part of the critical path of the activity network. 10 A 10 0 50 C 30 20 20 B d 10 Duration Ear
Questions, mark schemes and examiner’s reports are © AQA, from their published past papers. Plumi isn’t affiliated with any exam board. Want whole papers? Every AQA A-Level Further Maths paper.
Rather write your answers by hand on iPad? Plumi marks them against the same mark schemes.